Decision details

Kirklees Active Travel Fund; Tranche 2

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

In November 2020 the government confirmed the awards to local authorities as part of Tranche 2 of the Active Travel Funding. Tranche 2 was allocated to local authorities to provide facilities to support safe walking and cycling. As part of Tranche 2 allocations form the Active Travel Fund, Kirklees has received £1.9 Million.

 

The purpose of this report is to inform the Cabinet of the current status of the Active Travel Fund Tranche 2 Programme for Kirklees District and to seek relevant authorities to proceed by undertaking activities such as receipt of grant monies, feasibility design, consultation and engagement and delivery.

 

Decision:

RESOLVED –

 

1)    That the Huddersfield Narrow Canal (HNC) project which is to be carried out by the Canal & River Trust be endorsed.

2)    That approval be given to enter into a grant agreement with the West Yorkshire Combined Authority (WYCA) for the carrying out of the HNC project.

3)    That authority be delegated to the Strategic Director Growth & Regeneration to negotiate and agree the terms of that grant agreement with WYCA.

4)    That approval be given to enter into a funding agreement with the Canal & River Trust for the carrying out of the HNC project.

5)    That authority be delegated to the Strategic Director Growth & Regeneration to negotiate and agree the terms of that funding agreement with the Canal & River Trust.

6)    That authority be given to the Service Director Legal Governance & Commissioning to enter into and execute any grant agreement and funding agreement referred to in (2) and (4) above together with any ancillary documents.

 

Report author: Tim Lawrence

Publication date: 24/06/2021

Date of decision: 22/06/2021

Decided at meeting: 22/06/2021 - Cabinet

Effective from: 30/06/2021