Cabinet will be asked to consider Streetscene
- Parks & Greenspace - Capital Priorities Programme
(1) That approval be given to the expenditure of £150,000 capital funding in order to upgrade and improve provision and the £101,500 Section 106 monies as outlined in the work programme and set out within the considered report in relation to the Parks and Greenspace refurbishment programme for 2016/2017.
(2) That authority be delegated to the Head of Environment and Greenspace to authorise works.
Report author: Rob Dalby
Publication date: 11/02/2016
Date of decision: 09/02/2016
Decided at meeting: 09/02/2016 - Cabinet