To seek a Cabinet decision regarding the
provision of a new 420 place primary school building to serve North
Huddersfield area.
That Cabinet:-
1.
Approved an overall capital allocation of £9.7m from the
Council’s Capital Plan for the project as defined in the
report, to create a new 420 place primary school building and
associated facilities at Clare Hill, Edgerton to serve Huddersfield
North;
2.
Approved the proposed mix of government grant, Section 106 monies
and prudential borrowing as detailed in sections 2.20-2.23 and
Appendix B of the report;
3.
Noted the information contained in Appendix B of the report which
detailed the name of the successful contractor and the agreed
contract price, which has been determined through a competitive
tender exercise in accordance with the Council’s Financial
and Contract Procedure Rules; and
4. Delegated authority to the Service Director, Legal, Governance and Commissioning, in consultation with the Service Director, Commercial, Regulatory and Operational Services, to finalise and enact all contractual agreements in relation to the building contract and the land purchase.