To consider the approval of potential projects, to be funded from the 2020/21 Achieve & Aspire Capital Maintenance section of the Capital Plan.
Contact: Jonathan Quarmby/David Martin, Corporate Landlord
Wards affected: All
Additional documents:
Decision:
1) That approval be given to the business case at Appendix A of the considered report, which outlines the rationale for the schools’ condition works programme, the availability of funding, the selection process and the main categories of work, thereby enabling the projects concerned to be designed, procured and implemented.
2) That approval be given to the detailed list of proposed works in schools for 2020/2021, as set out as Appendix B of the considered report.
3) That approval be given to the delegation of powers (as set out in paras 2.11 to 2.13 of the considered report) to the Service Director (Economy and Skills) to manage the implementation of the identified works within the respective agreed total programme budget.