To consider the proposed allocation of 2024/25 capital funding from the Directorate for Children’s Achieve & Aspire baseline section of the Capital Plan.
Wards affected: all
Contact: Emma Griff, Strategic Manager Facilities - Property
Additional documents:
Decision:
RESOLVED –
1) That approval be given to the business case as at Appendix A of the considered report which outlined the rationale for the schools’ condition works programme, the availability of funding, the selection process and the main categories of work, enabling the projects concerned to be designed, procured and implemented.
2) That approval be given to the detailed list of proposed works in schools for 2024/2025, as at Appendix B of the considered report.
3) That authority be delegated to Service Director for Development, Growth and Regeneration to manage and implement the identified works within the agreed total budget programme budget.