Agenda item

Corporate Financial Management - Quarter 1 Report

The Committee will a report in respect of the Corporate Financial Monitoring Report for Quarter 1, 2023/24 and a verbal update in respect of the Medium Term Financial Statement.

 

Contact: Service Director, Finance/Section 151 Officer.

Minutes:

The Committee received a report in respect of the Corporate Financial Monitoring Report for Quarter 1, 2023/24 and a verbal update in respect of the Medium-Term Financial Statement.

 

Councillor Graham Turner, the Portfolio Holder for Finance and Regeneration, introduced the report…..?. Rachel Spencer-Henshall, the Strategic Director for Corporate Strategy, Commissioning and Public Health and Isabel Brittain, the Interim Service Director, Finance attended the meeting and a presentation was given which highlighted the following:

Headlines from the Quarter 1 report and actions

Overview by Directorate

Service variances

Issues??

Recommendations approved by Cabinet – mitigations

….

The MTFS aimed to establish a framework to ensure delivery against savings

Subject of a debate at Council on 13th september

Ensure activity to resolve immediate issue of anticipated? forecast budget gap in 2024/25. And robust proposals were being …. To ensure a balanced budget by February 2024.

Current view that budget gap could be £ by 2028/29.

 

Questions and comments were invited from Committee Members, with the following issues being covered:

Exploring the potential of spend to save in respect of transport costs

investment to save was a potential and any scheme would look at if initial investmentwould pay didvidend in the long-ter, The Corporate Transformation Team -strategy- if can deliver early on some savings use??

Partnerships with other bodies such as the Woodlands Trust to assist with the projected overspend on tree planting??

The Council did work alongside partners on …more detail could be provided to members further to the meeting.

Access bio-diversity net gain funding

Potential revenue generator?

Cost-benefit analysis in respect of challenges in relation to proposals to reduce care packages for high cost children with disabilities placements.

Agree and approach would be to work within framework so individual response made in each case – reassure move from one size fits all approach

Clarity in respect of the differences between the current figures and the figures considered?submitted to by Council in February. An undertakeing was given to provide this detailed information after the meeting.

Whether the savings forecanst?? Wre achievable and when would the authority be in a position to have more certainty on this. The Service Director gave assurance that she would be undertaking a deep-dive into the …savings and their impact and would have more clarity by the end of the week???

Opportunities to achieve more income; flexibility to address issues. It was important that the issue of capacity was considered within questions relating to recruitment to ensure that the Council would still be able to tae advantage of opportunities. Assurance that the panel responsible for assessing vacancies would take into account the importance of not having a negative impact on income. Capacity would also be considered to try and ensure that resources were utilised in the best possible way.

 It was believed that there should be systematic approach to identifying opportunities for funding; including by/through partners and the community and voluntary sector who would have access to funding that was not available to the Council. This should be transparent and involve wider input, such as from Councillors. It was noted that this could be a challenge under the current system of bidding for pots of national funding as there had to be an appropriate level of payback balance between cost of submitting a bid which only some authorities would be successful ; it was considered a better use of resources to concentrate on those where there was a bigger chance of success…there were also issues associated with the challenging timescales both for the submission of bids or by which the funding must be used. robust due diligence… was commeunications with peers and other parties on this subject. The connectivity and working with the community and voluntary sector was strong.

It was noted the Committee had identified at the issue of procurement and external funding within its work programme for 2023/24.

In terms of the effectiveness of processes associated with reducing spend; it was believed that there was a strong financial team with a robust approach. Detail was being examined as the authority moved towards Quarter 2 and further information would be provided to the Committee at future meetings.

The regeneration proposals

Profile and demand for social care needs? Had been forecast to the best of the authoriy’s ability but this was challenging due to the many factors that influenced it.

The population of people with special educational needs and disabilities was/had increased and investment was being made into schools to increase capacity.

The Huddersfield Blueprint regeneration proposals had been calculated into the Capital Plan; this would be included in the review of overall spending.

The George Hotel project was being undertaken with partners and exterbal funding and….

There was a wish/need to invest to save and to increase the Council’s future income.

The Department for Education had ahreed and supported the Council’s approach in respect of the ‘safety valve’ for children and families budgets???

Deliver against agreement and the auditors were also happy… although it was not possible to predict levels of demand.

The Council had a robust SEND transformation programme in place??

Queried whether land that was/would not being used for a period of time could be used to increase the amount of parking in Huddersfield town centre, this would also generate additional income.

The Medium Term Financial Statement (MTFS) provided the principles and frameworj for the budget for next year and part of the engagement with Councillors and residents on the detail was an integral part of the approach. The underlying detail on delivery going forward was being…worked upon??

There was a clear approach in terms of achieving efficiencies to ensure that the needs of each service was ….. to ensure that valuable corporate memory was not lost. There was also a focus upon the development of graduate opportunities and University placements so that the next generation of staff in areas where recruitament could be a challenge could be established/built.

 

Resolved –

(1) That further information on the position at Quarter 2, the achievability of savings and detail of the re-profiling of the Capital Plan be provided to Members of the Committee at the earliest possible opportunity.

 

(2) That it be noted that the following issues were included within the Committee’s Work Programme for 2023/24:

(i)       Procurement and external funding. The report should include visibility and understanding of the work to identify and decide upon appropriate…..

(ii)       The approach to Asset Management.

(iii)      IT strategy were on the Committee’s work programme for 2023/24.

 

Supporting documents: