Agenda item

Funding associated with Huddersfield Open Market, Penistone Rail Line, Dewsbury Long-term plan and West Yorkshire Investment Zone; and delivery of Growth & Regeneration portfolio

To consider funding and recent grant allocations to support the delivery of Huddersfield Open Market, Penistone Rail Line, Dewsbury Long-term plan and West Yorkshire Investment Zone.

 

Wards affected: all

 

Contacts:

Huddersfield Open Market Regeneration

Sarah Collins – Programme Manager, Town Centre Programmes

 

Penistone Line rail upgrade

Joanna Ward – Transport Strategy & Policy Manager

 

Dewsbury – Long-term plan for Towns

David Wildman – Strategic Partnership Lead, Town Centres

 

Investment Zone / Station to Station Enterprise Corridor

Chris Duffill – Head of Business, Economy & Growth

 

Delivery support

Edward Highfield – Service Director, Skills and Regeneration

Decision:

RESOLVED –

 

1)    That the external Levelling Up Funding Round 3 of £16,649,855 from Department of Levelling Up, Housing and Communities (DLUHC) to support the delivery of Huddersfield Open Market Hall Levelling Up project, subject to the terms and conditions of the grant funding agreement, be accepted.

2)    That the external Levelling Up Funding Round 3 of £47,917,122 from DLUHC to support the delivery of Penistone rail line upgrade, subject to the terms and conditions of the grant funding agreement, be accepted.

3)    That the external funding of up to £20m (£15m for Capital, and £5m for Revenue) from DLUHC for the development and delivery of the Long-term plan for Dewsbury, subject to the terms and conditions of the grant funding agreement be accepted and that upon acceptance, the £15m would form part of the Council’s Capital Plan.

4)    That the external capital funding of up to £17m from DLUHC, via West Yorkshire Combined Authority (WYCA) as Accountable Body, to develop and deliver Kirklees projects within the West Yorkshire Investment Zone, subject to the terms and conditions of the grant funding agreement be accepted and that upon acceptance, this would form part of the Council’s Capital Plan.

5)    That in accordance with Sections 22.4 to 22.8 of the Financial Procedure Rules grant funding would be accepted for external capital and revenue funding for Kirklees projects within the West Yorkshire Investment Zone from DLUHC via WYCA as Accountable Body, should this become available and subject to any related terms and conditions.

6)    Pursuant to (5) above, subject to this funding, authority be given to officers to progress projects within the Investment Zone.

7)    That authority be delegated to the Strategic Director Growth and Regeneration and the Service Director Legal, Governance and Commissioning, in consultation with relevant Portfolio holders, to finalise and execute all necessary legal agreements and to put in place the necessary governance and assurance arrangements including entering into any grant agreements with DLUHC and WYCA to facilitate delivery of the above projects.

8)    That authority be delegated to the Strategic Director Growth and Regeneration, in consultation with relevant Portfolio holders, to develop and deliver the identified schemes for Huddersfield Open Market, the Penistone rail line upgrade and Kirklees projects within the West Yorkshire Investment Zone.

9)    That pursuant to (8) above, to include the preparation and submission of necessary statutory consents to ensure delivery and undertake the necessary procurement exercises, including the award of related contracts to deliver the projects, subject to necessary consents and approvals being in place and in accordance with the Council’s Contract and Financial Procedure rules.

10)That authority be delegated to the Strategic Director Growth and Regeneration, in consultation with the Portfolio holder, to work with the existing Dewsbury Town Deal Board to establish a new Town Board by 1 April 2024, with the Council continuing to act as Accountable Body, and for officers to work with the Board and Portfolio holder to develop and submit a Long-term Plan by 1st August 2024.

11)That authority be delegated to the Strategic Director Growth and Regeneration, in consultation with relevant Portfolio holders, to progress all necessary delivery arrangements including procurement and award of a contract to a Strategic Delivery Partner to provide professional services that facilitate the effective delivery of the project portfolio, and that authority be given to the Strategic Director for Growth & Regeneration, in consultation with the Portfolio Holder and the Service Director Legal, Governance and Commissioning to finalise and execute all necessary contract agreements.

Supporting documents: