The Panel were advised that:
- The original Playable Spaces
strategy was approved by Cabinet in 2019 to improve play quality
across Kirklees, provide a financially sustainable network, and
deliver benefits such as health, wellbeing, and community
cohesion.
- Version 1 (March 2019) proposed
converting local play areas to open greenspace with investment
focused on Community and Destination sites; Version 2 (October
2019) allowed traditional equipment at all sites if requested by
local communities.
- The programme launched in 2020 with
£3.9m capital invested and £5.6m committed or
allocated. Five years into delivery, expectations remained high,
but resources were restrictive.
- Kirklees managed 314 play areas,
significantly more than other local authorities, with 252 sites
over 15 years old included in the original programme.
- Benchmarking was undertaken against
other West Yorkshire authorities, and the Play Maintenance Team
consisted of four inspectors, supported by a small construction
team. Maintenance budgets were limited to £16,000 plus income
generation.
- Achievements included 41% programme
completion, with 59 sites completed and 43 in progress. Play value
increased by 141% on average at completed sites, and £782k
additional funding was secured.
- Challenges included:
- Increased material and staffing
costs, reducing value for money.
- Higher expectations as traditional
equipment was retained without additional funding.
- Restricted variety of facilities due
to budget constraints.
- Reduced workforce and maintenance
budgets impacting timelines and upkeep.
- Cost comparisons showed significant
price increases for equipment and surfacing since 2020, with
community play area costs rising by 41%.
- Next steps included gathering
feedback from the Scrutiny Panel, reviewing options for remaining
sites using an asset-led approach, and considering strategy
modifications for Cabinet in late summer 2026.
The Panel noted the presentation and, during
the subsequent discussion, raised the following questions and
points.
- In response to questions from the
Panel in relation to the budget and potential scope to work with
Public Health to increase flexibility, it was advised that the
programme had been entirely council and community- led. As a
result, this was how areas had been chosen for uplift. It was noted
that there was now an opportunity for flexibility and to identify
whether the project could be needs-led.
- In response to questions from the
Panel in relation to the role of planning, it was explained that
the reshaping the strategy had to be done in partnership with the
Planning Department and was being developed alongside the Local
Plan. The strategy had supported the Council to prevent developers
from placing play equipment within estates and to secure Section
106 funding for more appropriate locations.
- In response to questions from the
Panel in relation to Section 106 funding, it was noted that
discussions had begun to improve agreements and ensure wording
around children’s play was appropriate to achieve better
outcomes within legal agreements. The Panel noted the response, and
it was agreed that work continue to explore how use of the correct
wording in supplementary planning documents could support better
outcomes for Playable Spaces in the development of the
strategy.
- In response to questions from the
Panel in relation to commitments and managing expectations, it was
acknowledged that engagement with communities was impacted by
capacity and resourcing and that there was a need to ensure
capacity for commitment before engaging with the public or elected
members to maintain positive relationships. It was agreed that it
was important to set expectations and aspirations in line with
available resources and that the approach should remain realistic
to avoid doing too much at once and to identify any potential
long-term funding gaps. Conversations with Cabinet regarding
resource gaps and potential changes in direction were expected to
begin after summer.
- In response to concerns raised by
the Panel around elongating the programme, and how this could
result in newer play areas requiring maintenance later, it was confirmed that safety could be maintained
and the aspiration was for all play areas to be inviting and have
good play value, however, ideal quality
may not be guaranteed due to budget constraints, but these gaps
would be addressed as part of the strategy refresh.
- In response to concerns raised by
the Panel regarding the pace of the project, it was acknowledged
that thorough engagement, high level consultations and efforts to
reduce costs had contributed to the delays. The speed of the
programme delivery was being assessed as part of the strategy and
options included site-specific consultations and streamlining
processes rather than applying a one-size-fits-all approach.
- In response to questions from the
Panel in relation to environmental impact, it was advised that the
scheme continually identified recycling and refurbishment
opportunities and explored environmentally friendly surfaces in
play spaces. Biodiversity was also considered on a site-by-site
basis within maintenance constraints.
- In response questions from the Panel
regarding how play value was quantified, it was agreed that details
of the technical assessment used for playable spaces would be
shared with the Panel. The Panel noted the response and further
suggested that recording visitor numbers at each play area would
support robust data collection and rationale for investment. In
response it was advised that discussions with other local
authorities were taking place to identify effective solutions for
collecting this type of data.
- In response to questions from the
Panel in relation to the removal of a rope swing due to damage, it
was advised that work was underway to make budgets more sustainable
and that conversations with the Cabinet would begin to create
direction to review budgets.
- In response to questions from the
Panel in relation to play provision in town centres, it was
confirmed that as part of Cultural Heart investments, consideration
was being given to introducing play in town centres, ensuring
safety and sustainability. Comparisons with Manchester and other
cities would inform this work as part of wider town centre
regeneration.
The Panel noted the Playable Spaces presentation,
and it was recommended that:
RESOLVED:
(1)
Work be undertaken to explore how use of the correct wording in
supplementary planning documents could support better outcomes for
Playable Spaces in the development of the strategy.
(2)
Work be undertaken to ensure that aspirations were aligned with the
available resources and that any potential funding gaps be
identified.
(3)
Details of the technical assessment used for Playable Spaces be
shared with the Panel.
(4)
Work be undertaken to explore how visitor numbers to play spaces
can be recorded and how this data can be used to support future
investment.