Instruct the enabling works for Phase 1 of Our Cultural Heart (OCH)

15/02/2024 - Instruct the enabling works for Phase 1 of Our Cultural Heart (OCH)

To instruct the Phase 1 enabling works to ensure timely progress on Phase 1 of the development.

 

The enabling works form part of the £6.180m Pre-Construction Services Agreement(PCSA) budget. This budget covers the period up to starting the main construction works on site.

 

At the time of the Cabinet report the enabling works were budgeted at £1.105m. The scope of the works now includes additional items and the value that will be instructed is £1.281m. However, the original PCSA budget of £6.180m will be maintained with the difference of £176k being funded from reallocation of monies from within the PCSA budget.

 

The works will be carried out between the 11thMarch and the 10thJune 2024. The main construction works are then programmed to commence on the 10thJune subject to agreement on the contract sum, all as set out in the Cabinet report