2025/26 - 2026/27 Corporate Landlord Capital Plans - Proposed allocation of capital funding

09/07/2025 - 2025/26 - 2026/27 Corporate Landlord Capital Plans - Proposed allocation of capital funding

RESOLVED –

 

1)    That the programmes of work for 2025/26 – 2026/27 as shown in Appendix be approved.

2)    That authority be delegated to the Service Director – Development in consultation with the Portfolio Holder to: -

 

(i)             add or delete projects from the programmes, provided that the total cost of the programmes remains within the approved capital allocations,

(ii)            transfer resources between the Corporate Landlord programmes without restrictions,

(iii)          slip, delete or reallocate budget between projects during the two financial years, provided that the total cost of the programmes remains within the approved capital allocations.

 

3)    To approve acceptance and addition to the Capital Plan of £76,006 (retrospective for £68,405 already applied in 2024/25) grant from Sport England and £100K capital from the Trustee of Clayton West to be vired into the Scissett Baths budget as agreed contributions.