The contractor (BAM) is already working under the PCSA to deliver the RIBA 4 stage design, negotiate the NEC construction contract and the associated contract sum and carry out the already instructed enabling works.
The PCSA period is to be extended by five weeks to the 12th July 2024 to allow the construction contract and the associated contract sum negotiations to be concluded.
At the same time, to utilise the contractor resources efficiently and to maintain the programme, further internal demolition works are to be instructed under the PCSA. These works are part of the demolition works that were intended to be carried out during the next stage of the delivery programme under the NEC construction contract.
Funding of £348,093 to cover both these items will be drawn from the approved construction stage budget.
This decision takes effect from the 7th June 2024.
Background information
Decision type: Non-key
Decision status: Recommendations Approved
Wards affected: Newsome;
Notice of proposed decision first published: 07/06/2024
Decision due: 7 Jun 2024 by Strategic Director for Growth and Regeneration
Lead member: Leader of the Council
Lead director: Strategic Director for Growth and Regeneration
Department: Finance and Regeneration
Contact: David Glover Email: david.glover@kirklees.gov.uk.
Members/Officers Involved: David Shepherd, Kavin Mulvaney