Our Cultural Heart (OCH) Phase 1, Structural works to the former Queensgate Market

The report that accompanies this decision is supplementary to the Phase 1 Gateway 4 Cabinet report (December 2023), below is the executive summary.

 

To protect the asset value and amenity and provide longevity of the Grade II listed former Queensgate Market (the building), parts of the concrete structure need replacement, repair and/or strengthening.

 

The additional structural works (the works) are required regardless of the buildings end use and therefore the proposal is to instruct them under the Phase 1 JCT Design & Build construction contract (main contract) with BAM Construction Limited (BAM) that is due to be awarded in July 2024.

 

Instructing the works through the proposed main contract, when BAM are already on site carrying out other planned works, will be cost effective and will ensure that there isn’t a delay to the delivery and operation of Phase 1 of Our Cultural Heart.

 

Decision type: Non-key

Decision status: Recommendations Approved

Wards affected: Newsome;

Notice of proposed decision first published: 02/07/2024

Decision due: 9 Jul 2024 by Leader of the Council

Lead member: Leader of the Council

Lead director: Service Director - Skills & Regeneration

Department: Finance and Regeneration

Contact: David Glover Email: david.glover@kirklees.gov.uk.

Making Representations: david.glover@kirklees.gov.uk

Members/Officers Involved: Cllr Cathy Scott - Leader of the Council David Shepherd - Strategic Director Growth & Regeneration David Glover - Senior Responsible Officer Our Cultural Heart