Our Cultural Heart (OCH). Phase 1 - Extend the Pre-Construction Services Agreement (PCSA) period - Instruct further demolition works under the PCSA

The contractor (BAM) is already working under the PCSA to deliver the RIBA 4 stage design, negotiate the construction contract and the associated contract sum and carry out the already instructed enabling works.

 

The PCSA period is to be extended by three weeks to the 2nd August 2024 to allow the construction contract to be concluded.

 

At the same time, to utilise the contractor resources efficiently and to maintain the programme, further demolition works are to be instructed under the PCSA. These works are part of the demolition works that were intended to be carried out during the next stage of the delivery programme under the construction contract.

 

Funding of £396,071 to cover both these items will be drawn from the approved construction stage budget as per the current cashflow.

 

This decision takes effect from the 15th July 2024.

 

Decision type: Non-key

Decision status: Recommendations Approved

Wards affected: Newsome;

Notice of proposed decision first published: 06/07/2024

Decision due: 5 Jul 2024 by Strategic Director for Growth and Regeneration

Lead member: Leader of the Council

Lead director: Strategic Director for Growth and Regeneration

Department: Finance and Regeneration

Contact: David Glover Email: david.glover@kirklees.gov.uk.

Members/Officers Involved: David Shepherd, David Glover, Cllr Cathy Scott