On the 14th October 2021 an Agreement for Lease was entered into between the Council and Keepmoat Homes in respect of the land off Soothill Lane, Batley.
Within this agreement the provision for affordable housing to be constructed as part of the development was set at 20% of the aggregate of all dwellings to be constructed on the land.
Bulk transfers have since taken place to Registered Providers which increased the Affordable Housing provision to 117 units in total through agreement with Homes England and formalised through Deed of Variations.
Keepmoat have now requested to transfer a further 19 additional affordable housing units to a Registered Provider. On 30th January 2026 Homes England approved this further increase in affordable housing and this brings the total to 136 affordable units out of 319 units across the full site.
A Delegated Decision Notice is now required to enter into the appropriate Deed of Variations with both Homes England and Keepmoat to progress this.
There is no financial impact to the Council and the costs of the additional affordable units are being met by the Registered Provider utilising Home England funding.
Decision type: Non-key
Decision status: Recommendations Approved
Wards affected: Batley East;
Notice of proposed decision first published: 13/03/2026
Decision due: 30 Jan 2026 by Executive Director for Place
Lead member: Portfolio Holder - Finance & Regeneration
Lead director: Executive Director for Place
Department: Finance and Regeneration
Contact: Liz Jefferson, Acting Head of Housing Growth 01484 221000 Email: liz.jefferson@kirklees.gov.uk.
Members/Officers Involved: Deputy Leader and Transport and Housing