RP Clusters Programme Option Agreement Extension

Housing Growth and Regeneration team have agreed with Thirteen Group to extend the option agreement date on the Highmoor Lane site which is parcelled in the RP Clusters Programme to allow for a period of contingency if there’s any delays encountered.


There is a risk that if the expiry date of the Option agreement is not extended, Thirteen Group will not be in a position to exercise the option before their expiry and therefore will be unable to proceed with their purchase and development of the site.

 

For Highmoor Lane, the below extension has been agreed.

 

Site

Expiry Date

Proposed Extension Date

Rationale

Highmoor Lane

30th June 2026

31st March 2027

Provide contingency period to resolve Planning matters, legal and sale negotiations.

 

Decision type: Key

Decision status: Recommendations Approved

Wards affected: Cleckheaton;

Notice of proposed decision first published: 02/07/2026

Decision due: 29 Jun 2026 by Service Director - Development

Lead director: Executive Director for Place

Contact: Rebecca Addy, Acting Strategic Partnership Lead - Housing Growth Email: rebecca.addy@kirklees.gov.uk.